Bouddi NP | |||
Half Tide Rocks Track | Stabilise and improve walking track in Bouddi NP. NPWS to consider stair alignment options. Have discussed with WTKCA, surveys completed. Concerned that geotech too risk averse - needs simpler solution. No design options or costs prepared as yet. | Propose alternative alignments and options. WTKCA offer to co-fund. | NPWS, WTKCA |
Where Half Tide Rocks Track
What Stabilise and improve walking track in Bouddi NP. NPWS to consider stair alignment options. Have discussed with WTKCA, surveys completed. Concerned that geotech too risk averse - needs simpler solution. No design options or costs prepared as yet.
Who Propose alternative alignments and options. WTKCA offer to co-fund.
Status NPWS, WTKCA
|
|||
Brisbane Water | |||
Ettalong Channel | Provide consistent maintenance dredging for ferries and recreational vessels. Survey completed Nov 2021. Dept of Transport, Dept of Environment, RMS and CCC have agreed a program of dredging and spoil deposit to nearby beaches. Expect works mid year. No dredging as planned, leading to shoaling and cessation of ferry services May 2023. Dredging tender released by TfNSW early August, no start date. Disruptions likely until October 2023. | Waiting on dredging to commence. Ettalong Patonga Shuttle bus and Wagstaffe Ettalong shuttle ferry services in place . | NSW Dept of Transport Marine Infrastructure Division. |
Where Ettalong Channel
What Provide consistent maintenance dredging for ferries and recreational vessels.
Survey completed Nov 2021. Dept of Transport, Dept of Environment, RMS and CCC have agreed a program of dredging and spoil deposit to nearby beaches. Expect works mid year.
No dredging as planned, leading to shoaling and cessation of ferry services May 2023. Dredging tender released by TfNSW early August, no start date. Disruptions likely until October 2023.
Who Waiting on dredging to commence. Ettalong Patonga Shuttle bus and Wagstaffe Ettalong shuttle ferry services in place .
Status NSW Dept of Transport Marine Infrastructure Division.
|
|||
Hardys Bay / Killcare | |||
Araluen Dr Killcare, east of Killcare Rd | Provide safe pedestrian access. Needs to be done in conjunction with parkland improvements and improvements to road alignment, road surface & parking. Resident petition seeking action. WTKCA supports in full, but insists that proper consideration be given to alignment of any walkway, including a boardwalk option similar to jetty construction. | Included in scope for local Foreshore Planning Group. Safety and Accessibility is key focus. | Foreshore Planning Group, Council. |
Where Araluen Dr Killcare, east of Killcare Rd
What Provide safe pedestrian access. Needs to be done in conjunction with parkland improvements and improvements to road alignment, road surface & parking. Resident petition seeking action. WTKCA supports in full, but insists that proper consideration be given to alignment of any walkway, including a boardwalk option similar to jetty construction.
Who Included in scope for local Foreshore Planning Group. Safety and Accessibility is key focus.
Status Foreshore Planning Group, Council.
|
|||
Toilet Block Araluen Dr, Hardys Bay (northern end) | Retain and refurbish for public amenity | Now refurbished. | Council |
Where Toilet Block Araluen Dr, Hardys Bay (northern end)
What Retain and refurbish for public amenity
Who Now refurbished.
Status Council
|
|||
RSL Creek, Hardys Bay | Improve cleanliness and drainage to bay. CCC reluctant to clear the drain-way through mangroves. Heavy rains made this improvement imperative as storm water not able to flow freely to bay. | Included in scope for local Foreshore Planning Group | Foreshore Planning Group, Council. |
Where RSL Creek, Hardys Bay
What Improve cleanliness and drainage to bay. CCC reluctant to clear the drain-way through mangroves. Heavy rains made this improvement imperative as storm water not able to flow freely to bay.
Who Included in scope for local Foreshore Planning Group
Status Foreshore Planning Group, Council.
|
|||
Araluen Dr north of Heath Rd | Replace water main. Delay through Aboriginal Heritage Approvals. Stage 1 to Otello followed by Stage 2 to Dog Track has been approved by CCC to apply for permit to dig. Works now complete. | Council. | |
Where Araluen Dr north of Heath Rd
What Replace water main. Delay through Aboriginal Heritage Approvals. Stage 1 to Otello followed by Stage 2 to Dog Track has been approved by CCC to apply for permit to dig. Works now complete.
Who
Status Council.
|
|||
Killcare Commercial Area | Investigate additional parking options. Off street anywhere? Between wharf and marina? | No action to date. Requires full design. Include in scope for local Foreshore Planning Group. | Foreshore Planning Group, Council. |
Where Killcare Commercial Area
What Investigate additional parking options. Off street anywhere? Between wharf and marina?
Who No action to date. Requires full design. Include in scope for local Foreshore Planning Group.
Status Foreshore Planning Group, Council.
|
|||
Waterfront parkland adjacent Araluen Dr Hardys Bay between Killcare Rd and Heath Rd | Improve parkland drainage, landscape & seawall. Needs co-ordination with road alignment works. Longer term - build new seawall and enlarge park, including beach steps near wharf. Design with raised planter beds accepted by CCC. Held up by Aboriginal heritage matters. Whole area in poor condition. Needs a full Masterplan. | No action to date. Requires full design. Include in scope for local Foreshore Planning Group. | Foreshore Planning Group, Council |
Where Waterfront parkland adjacent Araluen Dr Hardys Bay between Killcare Rd and Heath Rd
What Improve parkland drainage, landscape & seawall. Needs co-ordination with road alignment works. Longer term - build new seawall and enlarge park, including beach steps near wharf. Design with raised planter beds accepted by CCC. Held up by Aboriginal heritage matters. Whole area in poor condition. Needs a full Masterplan.
Who No action to date. Requires full design. Include in scope for local Foreshore Planning Group.
Status Foreshore Planning Group, Council
|
|||
Araluen Dr Hardys Bay, between Killcare Rd and Heath Rd | Improve road alignment, road surface & parking. Needs to be done in conjunction with parkland improvements. Needs minor re-alignment of existing kerb into parkland to widen prior to drain and tree after commercial area. To enable two way traffic in conjunction with parked cars, needs blocks removed after that point for full length and needs road surface levelling and no parking on residential side. Blocks moved inwards to parkland a slight improvement. Consider interim. | Requires full design. Included in scope for local Foreshore Planning Group | Foreshore Planning Group, Council. |
Where Araluen Dr Hardys Bay, between Killcare Rd and Heath Rd
What Improve road alignment, road surface & parking. Needs to be done in conjunction with parkland improvements. Needs minor re-alignment of existing kerb into parkland to widen prior to drain and tree after commercial area. To enable two way traffic in conjunction with parked cars, needs blocks removed after that point for full length and needs road surface levelling and no parking on residential side. Blocks moved inwards to parkland a slight improvement. Consider interim.
Who Requires full design. Included in scope for local Foreshore Planning Group
Status Foreshore Planning Group, Council.
|
|||
Killcare Heights | |||
Telecoms Tower | Telecoms tower for mobile services proposed to be erected on site of CCC water tank off Wards Hill Rd. Tower to initially service Telstra and Optus customers, with provision also for Vodafone. Approved by CCC and L&E Court, strong support from community. Further challenge from neighbour under Judicial Review. Still in Court Nov 2022. Hearing delayed until Mar 2023. DA rejected by court on legal technicality. Resubmitted by proponent. Under review by CCC Aug 2023. | Council will announce result and further approvals if given. | CCC |
Where Telecoms Tower
What Telecoms tower for mobile services proposed to be erected on site of CCC water tank off Wards Hill Rd. Tower to initially service Telstra and Optus customers, with provision also for Vodafone. Approved by CCC and L&E Court, strong support from community. Further challenge from neighbour under Judicial Review. Still in Court Nov 2022. Hearing delayed until Mar 2023. DA rejected by court on legal technicality. Resubmitted by proponent. Under review by CCC Aug 2023.
Who Council will announce result and further approvals if given.
Status CCC
|
|||
Pretty Beach | |||
Turo Park, Pretty Beach | Replace play equipment and relocate. New play space complete. WTKCA funded walkway. Now in operation. Install basketball practice hoop and backboard for older kids, enlarge existing concrete pad. Refine location of soccer net. Make park surface even. | Works commence mid August 2023 | Council |
Where Turo Park, Pretty Beach
What Replace play equipment and relocate. New play space complete. WTKCA funded walkway. Now in operation.
Install basketball practice hoop and backboard for older kids, enlarge existing concrete pad. Refine location of soccer net. Make park surface even.
Who Works commence mid August 2023
Status Council
|
|||
Pretty Beach Rd and adjacent seawall | Refurbish seawall and provide accessible pathway for full length | Requires full design. Added to scope of local Foreshore Planning Group | Foreshore Planning Group, Council |
Where Pretty Beach Rd and adjacent seawall
What Refurbish seawall and provide accessible pathway for full length
Who Requires full design. Added to scope of local Foreshore Planning Group
Status Foreshore Planning Group, Council
|
|||
Pretty Beach Pool | Clear and refurbish. Noted in CCC Green Spaces strategy. | No action to date. Requires full design. Include in scope for local Foreshore Planning Group. | Foreshore Planning Group, Council |
Where Pretty Beach Pool
What Clear and refurbish. Noted in CCC Green Spaces strategy.
Who No action to date. Requires full design. Include in scope for local Foreshore Planning Group.
Status Foreshore Planning Group, Council
|
|||
Surf Club Surrounds | |||
Killcare Surf Club Kiosk | Improve levels of grassed area, provide solid walkway towards southern end of beach, replace picnic table. Design prepared, KSLSC in agreement. Offer to fund by WTKCA through bequest. Follow through with CCC for approvals. | Waiting on CCC approvals. Approved in principle. | WTKCA leading the proposal to Council. |
Where Killcare Surf Club Kiosk
What Improve levels of grassed area, provide solid walkway towards southern end of beach, replace picnic table.
Design prepared, KSLSC in agreement. Offer to fund by WTKCA through bequest. Follow through with CCC for approvals.
Who Waiting on CCC approvals. Approved in principle.
Status WTKCA leading the proposal to Council.
|
|||
Killcare Surf Club grass adjacent to parking area | Provide shelter and BBQ facilities, replace old picnic tables. BBQ installed and operational. New picnic tables installed. Grass reinstated. Provide even, accessible pathway between carpark and BBQ end of park, adjacent to access road. | Request put to CCC by KSLSC and WTKCA. Waiting on response. | CCC |
Where Killcare Surf Club grass adjacent to parking area
What Provide shelter and BBQ facilities, replace old picnic tables. BBQ installed and operational. New picnic tables installed. Grass reinstated.
Provide even, accessible pathway between carpark and BBQ end of park, adjacent to access road.
Who Request put to CCC by KSLSC and WTKCA. Waiting on response.
Status CCC
|
|||
Traffic Management | |||
Empire Bay Dr Intersection | Improve arrangements for traffic exiting Wards Hill Rd onto Empire Bay Dr to reduce tailbacks and to improve safety. This could be a filter lane on Empire Bay Dr for traffic turning east or even a roundabout. A dual lane approach is required on Wards Hill Rd to separate traffic turning left and right. Option to use Poole Cl for left turning traffic onto Empire Bay Dr in addition to right turn filter lane. Letters written to local member. Past rejections by RMS, but need to keep pressure up. Local petition supported Dr Gordon Reid. Adam Crouch also pressing State Minister for action. | Waiting on responses and options from RMS | State Govt |
Where Empire Bay Dr Intersection
What Improve arrangements for traffic exiting Wards Hill Rd onto Empire Bay Dr to reduce tailbacks and to improve safety. This could be a filter lane on Empire Bay Dr for traffic turning east or even a roundabout. A dual lane approach is required on Wards Hill Rd to separate traffic turning left and right. Option to use Poole Cl for left turning traffic onto Empire Bay Dr in addition to right turn filter lane.
Letters written to local member. Past rejections by RMS, but need to keep pressure up. Local petition supported Dr Gordon Reid. Adam Crouch also pressing State Minister for action.
Who Waiting on responses and options from RMS
Status State Govt
|
|||
Wagstaffe | |||
Albert St Wagstaffe south of Mulhall St (unpaved) | Improve road surface and drainage. Currently gravel. Severe degradation after heavy rain. | Community petition April. Administrator and engineers came to site June. Surface re-profiled and drainage channel formed. Plan to refine profile and drainage Aug/Sep 2022. Potentially seal before end 2022. | Council. |
Where Albert St Wagstaffe south of Mulhall St (unpaved)
What Improve road surface and drainage. Currently gravel. Severe degradation after heavy rain.
Who Community petition April. Administrator and engineers came to site June. Surface re-profiled and drainage channel formed. Plan to refine profile and drainage Aug/Sep 2022. Potentially seal before end 2022.
Status Council.
|
|||
Wagstaffe Wharf | Refurbish walkway | No action by CCC to date. Adjacent low retaining wall renewed by WTKCA. | Council |
Where Wagstaffe Wharf
What Refurbish walkway
Who No action by CCC to date. Adjacent low retaining wall renewed by WTKCA.